Project budget (PM309000)

By using this window, you can do the following:
This topic provides information about the elements in this window in Visma Net, such as fields, field values, buttons, and check boxes.
  • Add and update budget records of any type for any project
  • View transactions and commitments that correspond to budget lines
  • Upload to and export budget lines of any type from Excel
  • Import and export budget lines of any type with the help of integration scenarios

The window toolbar

ElementDescription
View transactionsOpens the Project transactions (PM304000) window in a pop-up window. This window shows the list of project transactions that correspond to the selected budget line.
View commitment details

Opens the Commitments (PM306000) window in a pop-up window. This window shows the list of commitments that correspond to the selected budget line.

This button appears if at least one of the following check boxes is selected in the Project accounting preferences (PM101000) window: Internal cost commitment tracking or Revenue commitment tracking.

The table

ElementDescription
ProjectThe identifier of the project.
Project taskThe identifier of a project task. If you select a project that has the default project task, this task is automatically populated in the column.
Item IDThe item that is associated with the budget line. By default, the system populates this column with the empty item code, which is initially N/A and can be changed in the Empty item code field in the Project accounting preferences (PM101000) window.
Cost code

The cost code that is associated with the budget line. You can change the cost code value for each line.

The column is shown if the Cost code functionality is enabled in the Enable/disable functionalities (CS100000) window.

Account groupThe account group of the budget line.
DescriptionThe detailed description of the budget line.
UoMThe unit of measure of the budget line. If a stock item is selected in the Item ID column, the UoM column is automatically filled in with the base unit of measure of this stock item, which can be changed to another UoM available for the item.
Original budgeted quantityThe budgeted quantity of the budget line.
Unit rateThe price of the specified unit of the budget line.
Original budgeted amountThe budgeted amount of the budget line. For the original budgeted quantity, UoM, and unit rate specified for the line, the amount is calculated as Original budgeted amount = Original budgeted quantity * Unit rate.
Revised budgeted quantityIf the Change order workflow check box is cleared for the project on the Summary tab of the Projects (PM301000) window, you can change the quantity manually.
Revised budgeted amountThe revised budgeted amount if the original budget amount has been revised for the project after the initial budgeting. By default, this amount is equal to the Original budgeted amount value specified for the line.
Revised committed quantity

The quantity is updated only if the UoM is specified in the budget line and if the system can convert the UoM of the document line to the UoM of the budget line by using the list of unit conversions defined in the Units of measure (CS203100) window.

This column appears if at least one of the following check boxes is selected in the Project accounting preferences (PM101000) window: Internal cost commitment tracking or Revenue commitment tracking.

Revised committed amount

The total amount of commitments that are associated with the project, project task, and account group.

This column appears if at least one of the following check boxes is selected in the Project accounting preferences (PM101000) window: Internal cost commitment tracking or Revenue commitment tracking.

Committed revised quantity)

The total received quantity of the commitments that are associated with the project, project task, and account group.

This column appears if at least one of the following check boxes is selected in the Project accounting preferences (PM101000) window: Internal cost commitment tracking or Revenue commitment tracking.

The quantity is updated only if the UoM is specified in the budget line and if the system can convert the UoM of the document line to the UoM of the budget line by using the list of unit conversions defined in the Units of measure (CS203100) window.

Committed invoiced quantity

The total invoiced quantity of the commitments that are associated with the project, project task, and account group. This column appears if at least one of the following check boxes is selected in the Project accounting preferences (PM101000) window: Internal cost commitment tracking or Revenue commitment tracking.

The quantity is updated only if the UoM is specified in the budget line and if the system can convert the UoM of the document line to the UoM of the budget line by using the list of unit conversions defined in the Units of measure (CS203100) window.

Committed invoiced amount

The total invoiced amount of the commitments that are associated with the project, project task, and account group.

This column appears if at least one of the following check boxes is selected in the Project accounting preferences (PM101000) window: Internal cost commitment tracking or Revenue commitment tracking.

Committed open quantity

The total open quantity of the commitments that are associated with the project, project task, and account group.

This column appears if at least one of the following check boxes is selected in the Project accounting preferences (PM101000) window: Internal cost commitment tracking or Revenue commitment tracking.

The quantity is updated only if the UoM is specified in the budget line and if the system can convert the UoM of the document line to the UoM of the budget line by using the list of unit conversions defined in the Units of measure (CS203100) window.

Committed open amount

The total open amount of the commitments that are associated with the project, project task, and account group.

This column appears only if at least one of the following check boxes is selected in the Project accounting preferences (PM101000) window: Internal cost commitment tracking or Revenue commitment tracking.

Actual quantityThe total quantity of the lines of the released customer invoices that correspond to the budget line. The quantity is updated only if the UoM is specified in the budget line and if the system can convert the UoM of the document line to the UoM of the budget line by using the list of unit conversions defined in the Units of measure (CS203100) window.
Actual amountThe total amount of the lines of the released customer invoices that correspond to the budget line.
Type

The type of the account group of the budget line that can be one of the following:

Asset
The account group may include asset and liability accounts.
Liability
The account group may include liability and asset accounts.
Income
The account group may include income, expense and liability accounts.
Expense
The account group may include expense and income accounts.
Off-balance
The account group is used to track statistical information.

Related pages